A kitchen renovation is not one job. It is eight or nine separate trades that have to arrive in the right order, each waiting on the one before it. Get the sequence right and the whole thing moves quickly. Get it wrong and you are paying someone to come back a second time, or worse, undoing finished work.
Cabinetry sits near the end of that chain, which surprises people, because it is usually the first thing they start shopping for.
Why the order matters more than the pace
Almost every expensive renovation mistake is a sequencing mistake. Tiles laid before the cabinet layout was final. A power point rough-in positioned where a drawer bank now sits. A benchtop templated off a drawing rather than off installed cabinets.
None of these is anyone being careless. They happen because trades were booked in the order they became available rather than the order the job needed.
The order of works
A typical kitchen renovation in an existing home runs roughly like this.
- Design, measure and final sign-off. Everything downstream depends on this being locked, including appliance models.
- Permits, where required, before any structural or plumbing work begins.
- Demolition and strip out. This is also when hidden problems surface, so leave a little contingency here.
- Structural work, if walls are moving or an opening is being formed.
- Plumbing and electrical rough-in. Pipes and cabling go into open walls, positioned against the final cabinet layout.
- Plastering, patching and painting. Walls get finished while they are still easy to reach.
- Flooring, sometimes. See the next section, because this one is genuinely contested.
- Cabinet installation. Carcasses, doors and kickboards go in and are levelled.
- Benchtop template, fabrication and install. Templated off the installed cabinets, never off the plan.
- Splashback, then plumbing and electrical fit-off. Sink, tapware, appliances and switches are connected last.
The cabinetry stage itself is usually shorter than people expect. We have written separately on how long a cabinet installation takes, and the install is rarely the bottleneck.
The flooring decision that trips people up
Whether flooring goes in before or after the cabinets is the question we are asked most, and the honest answer is that it depends on the floor.
Tiles generally go down first, with the cabinets installed on top. It uses more tile, but it means the kickboards sit on a finished surface, and a future kitchen can be replaced without relaying the floor.
Floating floors are the opposite. They expand and contract with temperature and humidity, and they need to be free to move. Trapping a floating floor under a loaded run of cabinetry restricts that movement and can cause buckling across the room. These are normally laid after the cabinets, finishing against the kickboard.
Getting this wrong is not a cosmetic problem. It is the kind of mistake that shows up six months later as a lifted board in the middle of the living room, and the cause is rarely obvious by then.
The gap nobody plans for
Here is the stage that catches almost everyone. Benchtops cannot be templated until the cabinets are installed and levelled, and fabrication takes time after that. For that window, you have cabinets with no bench on them, no sink and no working kitchen. It is the least comfortable part of the job, and it is unavoidable, so it is worth knowing in advance rather than discovering. Lead times vary considerably by material and by whether the cabinetry is custom or stock, which we covered in our comparison of custom and stock cabinets.
Plan for it. Set up a temporary bench and a kettle somewhere else in the house before demolition starts, not during.
Who is licensed for what
Some of this sequence is not optional, and it is worth knowing who carries which obligation.
Victoria’s building and plumbing regulator is the Building and Plumbing Commission, which replaced the Victorian Building Authority in July 2025 and also absorbed domestic building dispute resolution and domestic building insurance. Electrical and gas work is licensed separately through Energy Safe Victoria.
Plumbing work above a set value requires a compliance certificate, which only a licensed plumber can issue and which must be lodged with the regulator within days of the work being finished. Electrical work requires a certificate of electrical safety from the licensed electrician. Keep both. They are your evidence at resale and your protection if something fails.
A kitchen renovation that keeps everything in place and simply replaces cabinets and benchtops often needs no building permit. Once walls move or plumbing relocates, that changes, and thresholds also apply to when a registered builder and a written contract are required. Confirm your specific job with your building surveyor rather than assuming, since the figures are periodically amended.
The detail that delays more kitchens than any other
Appliances. Cabinetry is built around them, not the other way round, so the exact models have to be confirmed before anything is manufactured. An oven cavity, an integrated dishwasher and a rangehood all have specific dimensions and clearances, and a substituted model can mean a remade cabinet. Have the specifications confirmed at design stage, and ideally the appliances on site before installation. What is and is not included in the cabinetry scope is worth clarifying early too, which we set out in our piece on what a full kitchen cabinet quote covers.
This sequencing work is most of what we do on renovations through Narre Warren and the established suburbs around it, where kitchens are being replaced in homes that are still being lived in. Our cabinet makers in Narre Warren page covers how we coordinate with the other trades on those jobs.
FAQs
Do I need a building permit to renovate a kitchen in Victoria?
Often not, if nothing structural moves and the plumbing stays where it is. Once you remove or alter a wall, or relocate plumbing, a permit is generally required and must be in place before that work starts. Permits are issued by a registered building surveyor rather than the council directly. Confirm your specific job rather than assuming, since the answer turns on the detail.
Should flooring go in before or after the cabinets?
It depends on the floor type. Tiles usually go down first, with cabinets installed on top. Floating floors normally go in afterwards, because they need room to expand and contract and should not be trapped under a loaded run of cabinetry. Decide this before anyone is booked, as it changes the order of the whole job.
How long does a kitchen renovation take from start to finish?
Longer than the install itself, which is the figure most people have in mind. The schedule is driven by the waiting periods between trades, particularly benchtop fabrication after templating, rather than by how long any single trade spends on site.
Who books the trades, me or the cabinet maker?
It depends on how the job is set up. On a full renovation, a builder usually coordinates everyone. On a cabinetry replacement, the homeowner often books the plumber and electrician directly. Either arrangement works, but it needs to be agreed at the start so the rough-in happens against the final cabinet layout rather than the old one.
When do appliances need to be on site?
The specifications need to be confirmed before manufacture, because cabinets are built to the appliance dimensions. The appliances themselves ideally arrive before installation. Changing an appliance model after cabinets are made can mean remaking a cabinet, which is one of the more avoidable delays in a renovation.
Quality Support Built Around Your Goals
Most of the cost and frustration in a renovation comes from trades arriving in the wrong order, and almost all of it is avoidable with a conversation at the planning stage rather than the booking stage.
If you are mapping out a kitchen renovation and want to know where cabinetry fits around your plumber, electrician and flooring, talk to us before you lock anyone in. We will tell you what has to happen first and where the waiting periods fall, so you can plan around them.
Call 0433 321 360 to walk through your timeline, or email your plans to admin@kitchendesigncabinets.com.au. Alternate line: 0433 559 121.
Kitchen Design Cabinets, 31 Tech Wy, Cranbourne VIC 3977. Custom kitchens, wardrobes, vanities, benchtops and splashbacks across Melbourne’s southeast.
kitchendesigncabinets.com.au